Here is a little brain teaser for you all...
Sven (Swede) planning to build a log splitter. Eventually he, later on, want to add a log lift and maybe a hydraulic 4 way wedge adjuster. He do not want to plumb the extra 2-spool valve at this moment.
Sven know he will have to do a power beyond addition, but he is not sure if the splitter valve should be upstream or down stream the additional 2-spool valve.
A:
If the splitter valve is placed up stream, he will need a splitter valve that is power beyond, PB, capable.
B:
If he choose to have the splitter valve down stream, his additional 2-spool valve need to be power beyond, PB, capable.
C:
It does not matter if splitter valve is up stream or down stream the additional 2-spool valve.
How should he best plan for the next addition of valves? A, B or C??
Please feel free to motivate your vote!
Sven (Swede) planning to build a log splitter. Eventually he, later on, want to add a log lift and maybe a hydraulic 4 way wedge adjuster. He do not want to plumb the extra 2-spool valve at this moment.
Sven know he will have to do a power beyond addition, but he is not sure if the splitter valve should be upstream or down stream the additional 2-spool valve.
A:
If the splitter valve is placed up stream, he will need a splitter valve that is power beyond, PB, capable.
B:
If he choose to have the splitter valve down stream, his additional 2-spool valve need to be power beyond, PB, capable.
C:
It does not matter if splitter valve is up stream or down stream the additional 2-spool valve.
How should he best plan for the next addition of valves? A, B or C??